CLEPMGT.014 Henry Gantt and Management Scheduling
0%
Skill Level🔴 Hard
00:00
Progress to Next Level25% to Medium
EasyMediumHardMastery100%

A baseline chart shows Vendor setup planned for Days 1-5, but the revised bar shows Days 1-8. Customer training is planned for Days 6-9 and depends on setup. What should the manager report?