A baseline chart shows Vendor setup planned for Days 1-5, but the revised bar shows Days 1-8. Customer training is planned for Days 6-9 and depends on setup. What should the manager report?
A
The chart proves the vendor intentionally caused the delay
B
Vendor setup has a three-day variance that threatens customer training unless the schedule is recovered
C
Customer training is unaffected because the baseline still says Day 6, carrying the conclusion into planning and implementation
D
Vendor setup is early because the revised bar is longer, treating that interpretation as the basis for the decision