CLEPMGT.190 Process Mapping, Flow, Bottlenecks, and Constraints
0%
Skill Level🔴 Hard
00:00
Progress to Next Level25% to Medium
EasyMediumHardMastery100%
The university financial-aid document check office is being balanced to meet a customer-demand takt time of 7 minutes per aid file. The process map shows cycle times: Document upload 6 minutes; Identity match 5 minutes; Eligibility review 5.5 minutes; Award update 9 minutes. Which step prevents the line from meeting takt time?