M202 Solve part-to-part and part-to-whole ratio problems
0%
Skill Level🔴 Hard
00:00
Progress to Next Level25% to Medium
EasyMediumHardMastery100%

For a project, the ratio of fixed cost to variable cost is 3:8. If the variable cost is reduced by $75 while the fixed cost stays the same, the ratio becomes 2:5. What was the original total project cost?